Metsä Fibre will start the preparatory work as a part of the pre-engineering at the Kemi mill area during July 2019. Preparatory work means the cleaning and organisation of land areas and the demolition of buildings. In addition, the electricity, IT and piping connections of the operational pulp and board mills in the planned bioproduct mill area will be organised.

Schnittholz

Metsä Fibre starts preparatory work at the Kemi mill in Finland

Metsä Fibre will start the preparatory work as a part of the pre-engineering at the Kemi mill area during July 2019, as the company says in the press release received by Lesprom Network.

Preparatory work means the cleaning and organisation of land areas and the demolition of buildings. In addition, the electricity, IT and piping connections of the operational pulp and board mills in the planned bioproduct mill area will be organised.

The preparatory work ensures the proficient progress of the construction works following the possible investment decision. The investment decision of the bioproduct mill is made earliest at the summer 2020, after which the construction of the new mill would begin. The new bioproduct mill could start up in the first half of the 2020s.

The 21 buildings to be demolished are mainly buildings that have remained unused for long periods of time and are partly in a poor condition. The municipality of Kemi granted a demolition permit in June 2019, and the demolition of these buildings does not require building permits for the new mill.

The preparatory work of the pre-engineering phase may cause occasional noise outside the mill area, generated by the chipping and crushing of concrete. Dust will be prevented from spreading by means of continuous watering. The work will continue until January 2020.

Metsä Fibre is a leading producer of bioproducts, bioenergy and sawn timber. Metsä Fibre is part of Metsä Group.