Caverion delivers process piping to Södra’s pulp mill at Värö, Sweden
Caverion has signed a contract with Valmet AB on the installation of mechanical process piping and equipment at Södra Cell AB’s pulp mill at Värö, Sweden. The contract covers multiple deliveries. Installation work started in spring 2015 and will be completed by spring 2016.
ByLesprom Network
Sep 04, 2015. /Lesprom Network/. Caverion
has signed a contract with ValmetAB on the installation of mechanical
process piping and equipment at Södra CellAB’s pulp mill at Värö, Sweden. The contract covers multiple
deliveries. Installation work started in spring 2015 and will be completed by
spring 2016, as the company says in the press release received by Lesprom
Network.
The process piping
delivery includes industrial installation projects at the pulp mill
causticising plant, fibre line and cooking plant. Caverion’s service chain
includes prefabrication, material procurement and installation for a total of
350 tonnes of piping.
Caverion’s deliveries
are part of Valmet’s deliveries to a major investment programme at Södra Cell’s
pulp mill. Södra Cell is investing about Euro 530 million to increase capacity,
optimise product quality and improve energy efficiency at the mill. Caverion
has been involved in Södra Cell’s previous pulp mill projects.
Our website uses cookies to make your browsing experience better and more personal. By using our site, you agree to our use of cookies. You can read our Cookie Policy and Privacy Policy.This website uses 'cookies' to give you the best, most relevant experience. You can read our Cookie Policy and Privacy Policy.