Assemblage of Euro 30 million PM 9 at Nemansky PPM completed
2006. Assemblage of PM 9 worth Euro 30 million is completed at Nemansky PPM.
May 12, 2006. /Lesprom Network/. Assemblage of PM 9 worth Euro 30 million is completed at Nemansky PPM, Kaliningrad region, Russia, (belongs to SZLC group of companies), SZLC public relations director Yuri Murashko said.
The beginning of start-adjusting works is set on May 22, 2006. Installation supervision is conducted by Voith specialists.
PM 9 was acquired in Great Britain in 2004. Its productive capacity is 60 000 tonnes of paper per annum. Productive capacity of Nemansky PPM after start-up of the new machine will total 130 000 tonnes of end-products annually.