Apr 11, 2008. /Lesprom.com/. The Board of Directors of United Fiber System Limited announced that its wholly owned subsidiary, PT Marga Buana Bumi Mulia has the agreement with China MCC20 Construction Co. Ltd for the construction of a bleached hardwood kraft pulp mill in South Kalimantan with a capacity of 600 thousand air dry tonnes per annum. The installation work required to set up a complete pulp mill for a consideration value of approximately $893 million. MCC20 shall be responsible for financing 75% of the total development costs in the form of a supplier’s credit and PT Marga Buana Bumi Mulia shall be responsible for the remaining 25%. The main machineries for the project are intended to be supplied by Andritz OY of Finland. The commencement of the work will take place within 90 days of the date of the contract. The mill is expected to be completed within 30 months.