Kruger announces holiday downtime at its paper mills in Quebec
Dec 22, 2009. Kruger Inc.'s Industrial Products Division will postpone by one week the temporary shutdown of Paper Machine No. 3 at its Wayagamack Mill and also confirmed the shutdown schedules for all its paper mills during the holiday season.
Dec 22, 2009. /Lesprom Network/. Kruger Inc.'s Industrial Products Division will postpone by one week the temporary shutdown of Paper Machine No. 3 at its Wayagamack Mill and also confirmed the shutdown schedules for all its paper mills during the holiday season, PaperAge reported.
Kruger Wayagamack Mill (Trois-Rivieres, Quebec) - the previously announced Paper Machine No. 3 (directory paper at shutdown has been postponed by one week; it will therefore begin on December 31 and last until February 23, 2010.
Coated paper production will be maintained without interruption through the holiday season.
All operations – newsprint, coated, supercalendered – at Trois-Rivieres Mill (Trois-Rivieres, Quebec) will be shut down for the statutory holidays: from December 24 to December 26 and from December 31 to January 4.
All operations (newsprint) At Brompton Mill (Sherbrooke, Quebec) will be shut down from December 24 until December 26, and will then run normally through the New Year.
All operations (newsprint) at Corner Brook Pulp and Paper (Corner Brook, Newfoundland and Labrador) will be shut down from December 24. Operations on Paper Machine No. 7 will resume on December 28, while Paper Machine No. 2 will restart on December 29.
Faced with persistently challenging market conditions, particularly the high value of the Canadian dollar, as well as weak demand and low prices, Kruger Inc. reduced production in all its publication paper mills in 2009. Overall production was cut by approximately 300,000 metric tonnes, with curtailments totaling 180,000 metric tonnes for newsprint, 80,000 metric tonnes for coated paper and 30,000 metric tonnes for supercalendered paper.
Three paper machines were also shut down for an indefinite period of time in 2009, namely one newsprint machine at the Corner Brook Mill and a supercalendered paper and coated production line at the Trois-Rivieres Mill.