Schweighofer's construction of its new sawmill in Romania progresses well
The construction of Schweighofer's new sawmill in Reci, Romania, are proceeding very well. At the moment the planing hall, the cutting hall and the kiln drying chambers are being built. Four of the total 9 pellets silos are also already under construction. The log place will follow in August. Start of operation will be in 1Q 2015.
ByLesprom Network
Jul 30, 2014. /Lesprom Network/. The construction of Schweighofer's new sawmill in Reci, Romania, are proceeding
very well. At the moment the planing hall, the cutting hall and the kiln drying
chambers are being built. Four of the total 9 pellets silos are also already
under construction, as the company said in the press release received by
Lesprom Network.
The log place will follow in August. Start of operation will be in 1Q 2015.
650 people will be employed in sawmill, therefore recruitment has
already started, in order to train the future staff properly.
Our website uses cookies to make your browsing experience better and more personal. By using our site, you agree to our use of cookies. You can read our Cookie Policy and Privacy Policy.This website uses 'cookies' to give you the best, most relevant experience. You can read our Cookie Policy and Privacy Policy.